Hi PMP aspirants, welcome to AKVTutorials. Seeking a resourceful platform that offers PMP practice questions to gauge your proficiency in Project Management Professional principles? Chart your course to PMP proficiency with our Practice Questions—a vital resource for Project Management Professional excellence. In this article, you will get Example PMP Exam Questions Prep Test 60. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
During planning phases, projects are baselined. After that, any proposed changes to those plans need to be carefully controlled and considered in the context of the overall project. This process is referred to as integrated change control. All of the following is true about this process except:
Option A : It occurs only at the end of the project.
Option B : It is the ultimate responsibility of external stakeholders.
Option C : It allows for changes to be captured using written or verbal formats.
Option D : It dictates that changes can be requested by any stakeholder.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
It dictates that changes can be requested by any stakeholder.
PMP Mock Test Question No 2
Which of the following is not true about schedule management on agile projects?
Option A : It uses longer cycles to undertake work, review results, and adapt
Option B : The role of the project manager is the same as it would be on a waterfall project
Option C : Rapid, frequent feedback is collected on deliverables
Option D : An on-demand, pull-based scheduling system is used
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
It uses longer cycles to undertake work, review results, and adapt
PMP Practice Exam Question No 3
In the middle of your project, you noticed that one of your sellers did not provide the materials that were needed by the deadline outlined in your agreement. You communicate this issue to the seller and remind them of the terms of the contract. In this scenario, what process was used?
Option A : Conduct Procurements
Option B : Control Schedule
Option C : Monitor & Control Project Work
Option D : Control Procurements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Control Procurements
PMP Mock Exam Question No 4
At this point on your project, you are in the process of planning how scope will be managed. Which of the following are inputs of that process?
Option A : Scope Management Plan, Project Charter, Business Documents
Option B : Quality Management Plan, Project Charter, Development Approach
Option C : Project Charter, Requirements Management Plan, Development Approach
Option D : Project Life Cycle Description, Stakeholder Engagement Plan, Quality Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Quality Management Plan, Project Charter, Development Approach
Project Management Professional Question No 5
You are soliciting advice from several experts, who have worked on similar projects, as you prepare the work breakdown structure (WBS). Which of the following is not a purpose of this document?
Option A : Articulate the components of work that will satisfy project objectives.
Option B : Subdivide the project work into more manageable components.
Option C : Outline the duration required to complete project activities.
Option D : Provide a hierarchical structure for assigning costs to work packages.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Outline the duration required to complete project activities.
PMP Certification Prep Question No 6
One of the stakeholders on the project approaches the project manager about a disagreement they had with the lead engineer. The stakeholder makes several accusations, and the project manager determines that they need to pause the discussion until they can gather more information about the encounter from the engineer. In this case, which conflict resolution technique was utilized?
Option A : Force/Direct
Option B : Withdraw/Avoid
Option C : Smooth/Accommodate
Option D : Compromise/Reconcile
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Withdraw/Avoid
PMP Exam Question No 7
A project manager has been assigned to lead an effort to design a new virtual reality headset. Early in the project; he identifies the processes, inputs, tools, and outputs that would be appropriate for his project. This identification process is known as which of the following?
Option A : Configuration Management
Option B : Project Tailoring
Option C : Deliverable Selection
Option D : Environmental Assessment
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Project Tailoring
PMP Exam Sample Question No 8
All of the following are true about cost plus incentive fee (CPIF) contracts except:
Option A : There may be price adjustments over time based on changes to certain financial indices.
Option B : The seller is reimbursed for all allowable expenses.
Option C : The seller is provided a bonus if certain predetermined objectives are achieved.
Option D : Incentives are awarded typically for meeting cost, schedule, or performance targets.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
There may be price adjustments over time based on changes to certain financial indices.
PMP Exam Practice Question No 9
Dylan is estimating costs on a project that involves configuring inventory management software for a clothing retailer. He decides to use examples from similar projects, which were performed in the past, to generate the estimate. In this case, what estimating technique is being used?
Option A : Bottom-Up Estimating
Option B : Analogous Estimating
Option C : Parametric Estimating
Option D : Three-Point Estimating
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Analogous Estimating
PMP Certification Exam Question No 10
A project to renovate an arena that hosts sporting events is ongoing. Currently, the team is performing the plan quality management process. In doing so, which of the following activities might they complete?
Option A : Determining if the deliverables are complete, correct, and compliant with appropriate standards.
Option B : Using audits to determine if activities on the project are conforming to organizational policies and then addresses gaps, if needed.
Option C : Determining appropriate investments in prevention and appraisal costs to avoid quality failures.
Option D : Using the six sigma methodology to identify process improvement opportunities.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Determining appropriate investments in prevention and appraisal costs to avoid quality failures.