Hi PMP aspirants, welcome to AKVTutorials. Ready to test your knowledge and skills with a diverse set of PMP Project Management Professional practice questions? Unearth the secrets to PMP success through our Practice Questions—an essential companion for every Project Management Professional aspirant. In this article, you will get Best PMP Exam Test Questions Paper 111. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
What is the meaning of ‘ethnocentrism’?
Option A : The acceptance of another culture.
Option B : The awareness of another culture but not necessarily the acceptance of that culture.
Option C : The acceptance of another culture as a function of doing business internationally.
Option D : The believe that your own culture is superior.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The believe that your own culture is superior.
PMP Exam Preparation Test Question No 2
You are teaching a class of junior project leaders the benefit of calculating and understanding schedule variance(SV).Your class is using the following value to determine the ‘health’ of project. PV=$220,000 EV= 200,000, AC=280,000. According to your analysis the SV and hence the status of the project is:
Option A : $20,000 the project is ahead of schedule.
Option B : -$20,000 the project is behind schedule.
Option C : -$80,000 the project is behind of schedule.
Option D : $60,000 the project is behind of schedule.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
$60,000 the project is behind of schedule.
PMP Exam Sample Exam Question No 3
As, the customer you have decided the contract out a scope of work that you are not able to define very well. You plan to be “hands on” and actively participate with your own forces during the performance of the work. Of the following contracts type, which would be the preferred contract type to select under this scenario?
Option A : CPPC
Option B : FFIF.
Option C : CPIF.
Option D : CPFF.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
FFIF.
PMP Certification Exam Question No 4
Customer risk is highest with:
Option A : Firm fixed price contracts.
Option B : Cost plus incentive fees.
Option C : Cost sharing.
Option D : Fixed price plus incentives
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Cost sharing.
Free PMP Practice Exam Question No 5
According to standard statistical control rules if the data result reflect 7 consecutive data points on either side of the mean, this tells you:
Option A : that the process is out of control.
Option B : that the process is in control.
Option C : that there is an abnormal trend which bears investigations.
Option D : that the process is cyclical.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
that the process is cyclical.
Best PMP Exam Practice Question No 6
A histogram that is order by frequency of occurrence and shows how many results were generated by type or identified cause is called a :
Option A : Statistical control chat
Option B : Ishikawa diagram.
Option C : Pareto diagram
Option D : Cause –and effect diagram.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Statistical control chat.
Free PMP Exam Prep Question No 7
In a matrix organization, both the functional and project manager shares certain responsibilities. Which of the following is not a responsibility of the project manager?
Option A : Complete task definition.
Option B : Resource requirement definitions.
Option C : Major timetable milestones.
Option D : personnel performance measurements.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
personnel performance measurements.
Latest PMP Exam Question No 8
What is unilateral contract?
Option A : a contract that has only one signature.
Option B : a purchase order.
Option C : a RFQ
Option D : a sealed bid
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
a contract that has only one signature
PMI PMP Exam Practice Question No 9
What is one of the ways that a contract typically does not end?
Option A : Successful performance
Option B : Mutual agreement.
Option C : breach.
Option D : extension.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Successful performance
PMP Certification Exam Agile Question No 10
Administrative closure includes all the following expert:
Option A : documentation of lesson learned.
Option B : verifying records including final; specification.
Option C : formal written notice to the contractor of project completion.
Option D : a collection of project reports.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a collection of project reports.