Hi PMP aspirants, welcome to AKVTutorials. Are you on the lookout for PMP Project Management Professional practice questions to validate your understanding of key concepts? Fast-track your PMP success with our Practice Questions—a comprehensive guide to mastering Project Management Professional concepts. In this article, you will get Best PMP Exam Questions Test Paper 59. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Which of the following is not true about procurement management on agile projects?
Option A : It is ideal when buyers and sellers are collaborating together in a virtual environment.
Option B : Specific sellers may be used to extend the team.
Option C : Buyers and sellers can collaborate to share risk and rewards.
Option D : Large projects may use agile for some deliverables and a more stable approach for others.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
It is ideal when buyers and sellers are collaborating together in a virtual environment.
PMP Mock Test Question No 2
While performing schedule management on your project, you need to determine the relationships between activities so that those activities are sequenced in the proper order. Which of the following is not true about activity sequencing?
Option A : It involves documenting the durations of activities.
Option B : It defines the logical sequence of work given certain constraints.
Option C : It helps build a realistic project schedule.
Option D : Every task (except for the first and last) should have both a predecessor and a successor.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
It involves documenting the durations of activities.
PMP Practice Exam Question No 3
On a construction project, it is a best practice to paint before you install appliances. This best describes which of the following dependencies?
Option A : Mandatory
Option B : Discretionary
Option C : External
Option D : Common
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Discretionary
PMP Mock Exam Question No 4
A project to construct a training environment for local firefighters has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. At this time, the scope is clearly defined, and the project manager does not expect any significant changes or the work to span multiple years. In this scenario, which type of contract should be utilized?
Option A : Firm Fixed Price (FFP)
Option B : Cost Plus Award Fee (CPAF)
Option C : Fixed Price with Economic Price Adjustment (FP-EPA)
Option D : Time & Materials (T&M)
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Firm Fixed Price (FFP)
Project Management Professional Question No 5
On a project to build a stage in an urban park that will be used for concerts and other performances, the team spends time defining how to conduct risk management on the project. What is an input that may be needed to perform this process?
Option A : Risk Register
Option B : Enterprise Environmental Factors
Option C : Risk Management Plan
Option D : Risk Report
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Enterprise Environmental Factors
PMP Certification Prep Question No 6
A commercial construction company that specializes in high-rise office buildings created a database to store project files from previous projects, such as completed project schedules from previous projects. This database would be considered which of the following?
Option A : An organizational process asset
Option B : A work performance report
Option C : An enterprise environmental factor
Option D : A lessons learned register
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
An organizational process asset
PMP Exam Question No 7
On an oil pipeline project, using a tool like Microsoft Project to create a “bottoms-up” schedule estimate would be included in which of the following skills sets in the PMI Talent Triangle®?
Option A : Project Management Information System
Option B : Leadership
Option C : Strategic and Business Management
Option D : Technical Project Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Technical Project Management
PMP Exam Sample Question No 8
A project to improve an insurance company’s algorithm for calculating accident risk is ongoing. Currently, the team is performing the plan scope management process. In doing so, which of the following activities might they complete?
Option A : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled.
Option B : Determining which of the documented requirements will be completed as part of the project.
Option C : Meeting with stakeholders to capture their needs and to ensure they are measureable.
Option D : Splitting the work of the project to make it easier to manage and monitor.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled.
PMP Exam Practice Question No 9
A project manager has evaluated the status of the project schedule and calculated a forecasted estimate to completion. This forecast would be considered which of the following:
Option A : Work Performance Information
Option B : Schedule Baseline
Option C : Work Performance Reports
Option D : Work Performance Data
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Work Performance Information
PMP Certification Exam Question No 10
You were recently hired by a mining company to lead a high priority project. Before moving forward, you understand that the structure of your organization will influence your work – whether for good or bad. The mining company is considered a projectized organization. Which of the following is not true about that organizational type?
Option A : Project managers hold more authority than functional managers
Option B : Resource availability for projects is low
Option C : Project managers control the budget
Option D : Project managers have roles that are full-time
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Resource availability for projects is low