Best PMP Exam Questions Test Paper 59

Hi PMP aspirants, welcome to AKVTutorials. Are you on the lookout for PMP Project Management Professional practice questions to validate your understanding of key concepts? Fast-track your PMP success with our Practice Questions—a comprehensive guide to mastering Project Management Professional concepts. In this article, you will get Best PMP Exam Questions Test Paper 59. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Which of the following is not true about procurement management on agile projects?

Option A : It is ideal when buyers and sellers are collaborating together in a virtual environment. 

Option B : Specific sellers may be used to extend the team. 

Option C : Buyers and sellers can collaborate to share risk and rewards. 

Option D : Large projects may use agile for some deliverables and a more stable approach for others.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

It is ideal when buyers and sellers are collaborating together in a virtual environment. 

PMP Mock Test Question No 2

While performing schedule management on your project, you need to determine the relationships between activities so that those activities are sequenced in the proper order. Which of the following is not true about activity sequencing?

Option A : It involves documenting the durations of activities. 

Option B : It defines the logical sequence of work given certain constraints. 

Option C : It helps build a realistic project schedule. 

Option D : Every task (except for the first and last) should have both a predecessor and a successor.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

It involves documenting the durations of activities. 

PMP Practice Exam Question No 3

On a construction project, it is a best practice to paint before you install appliances. This best describes which of the following dependencies?

Option A : Mandatory

Option B : Discretionary 

Option C : External 

Option D : Common

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Discretionary 

PMP Mock Exam Question No 4

A project to construct a training environment for local firefighters has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. At this time, the scope is clearly defined, and the project manager does not expect any significant changes or the work to span multiple years. In this scenario, which type of contract should be utilized?

Option A : Firm Fixed Price (FFP) 

Option B : Cost Plus Award Fee (CPAF) 

Option C : Fixed Price with Economic Price Adjustment (FP-EPA)

Option D : Time & Materials (T&M)

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Firm Fixed Price (FFP) 

Project Management Professional Question No 5

On a project to build a stage in an urban park that will be used for concerts and other performances, the team spends time defining how to conduct risk management on the project. What is an input that may be needed to perform this process?

Option A : Risk Register 

Option B : Enterprise Environmental Factors

Option C : Risk Management Plan

Option D : Risk Report

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Enterprise Environmental Factors

PMP Certification Prep Question No 6

A commercial construction company that specializes in high-rise office buildings created a database to store project files from previous projects, such as completed project schedules from previous projects. This database would be considered which of the following?

Option A : An organizational process asset 

Option B : A work performance report 

Option C : An enterprise environmental factor 

Option D : A lessons learned register

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

An organizational process asset 

PMP Exam Question No 7

On an oil pipeline project, using a tool like Microsoft Project to create a “bottoms-up” schedule estimate would be included in which of the following skills sets in the PMI Talent Triangle®?

Option A : Project Management Information System 

Option B : Leadership 

Option C : Strategic and Business Management 

Option D : Technical Project Management

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Technical Project Management

PMP Exam Sample Question No 8

A project to improve an insurance company’s algorithm for calculating accident risk is ongoing. Currently, the team is performing the plan scope management process. In doing so, which of the following activities might they complete?

Option A : Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled. 

Option B : Determining which of the documented requirements will be completed as part of the project. 

Option C : Meeting with stakeholders to capture their needs and to ensure they are measureable. 

Option D : Splitting the work of the project to make it easier to manage and monitor.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Determining how the project work; which will produce the desired products, services, or results; will be defined and controlled. 

PMP Exam Practice Question No 9

A project manager has evaluated the status of the project schedule and calculated a forecasted estimate to completion. This forecast would be considered which of the following:

Option A : Work Performance Information 

Option B : Schedule Baseline 

Option C : Work Performance Reports 

Option D : Work Performance Data

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Work Performance Information 

PMP Certification Exam Question No 10

You were recently hired by a mining company to lead a high priority project. Before moving forward, you understand that the structure of your organization will influence your work – whether for good or bad. The mining company is considered a projectized organization. Which of the following is not true about that organizational type?

Option A : Project managers hold more authority than functional managers 

Option B : Resource availability for projects is low 

Option C : Project managers control the budget 

Option D : Project managers have roles that are full-time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Resource availability for projects is low

PMP Exam Practice Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply