Best PMP Exam Practice Questions Test Paper 57

Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and in need of targeted practice questions for effective study sessions? Elevate your PMP expertise with our Practice Questions—an essential component for Project Management Professional triumph. In this article, you will get Best PMP Exam Practice Questions Test Paper 57. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

On a given project; earned value (EV) is $30,000; actual cost (AC) is $35,000; and planned value (PV) is $28,000. What is the cost performance index (CPI)?

Option A : 0.86

Option B : 1.16

Option C : 1.07

Option D : 0.93

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

0.86

PMP Mock Test Question No 2

At a company that assembles mobile phones, it was determined that automating the screen testing process could cut direct labor costs by $2,000,000 annually, so a project was initiated to do so. During the project, the team spends time performing project work (as defined in the plan) and implementing approved changes. What is an output from that process?

Option A : Accepted Deliverables 

Option B : Work Performance Data 

Option C : Approved Change Requests 

Option D : Meetings

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Work Performance Data 

PMP Practice Exam Question No 3

At a recent meeting on a project to identify and deploy a new inventory management tool, you inform your stakeholders that you are in the process of controlling procurements. What is an activity that could be performed during that process?

Option A : Confirming that payments are made to sellers as outlined in the terms of the contract. 

Option B : Preparing a request for information to get feedback from potential vendors. 

Option C : Defining the portion of scope that will be completed by outside vendors. 

Option D : Using advertisements to expand the pool of interested vendors

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Confirming that payments are made to sellers as outlined in the terms of the contract.

PMP Mock Exam Question No 4

At this point on your project, you are in the process of planning resource management. This involves documenting how you will estimate, acquire, and manage the labor and physical resources that will be needed. Which of the following are tools or techniques of that process?

Option A : Hierarchal Charts, Responsibility Matrix, Organizational Theory 

Option B : Pre-Assignment, Text-Oriented Formats, Meetings 

Option C : Colocation, Expert Judgment, Conflict Management 

Option D : Organizational Theory, Virtual Teams, Negotiation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Hierarchal Charts, Responsibility Matrix, Organizational Theory 

Project Management Professional Question No 5

A technology company was recently acquired so they are undertaking a project to transition payroll systems. At various points during the project, the team spends time monitoring project costs and carefully managing changes to the cost baseline. What is an output from that particular process?

Option A : Work Performance Data 

Option B : Approved Change Requests 

Option C : To-Complete Performance Index 

Option D : Work Performance Information

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Work Performance Information

PMP Certification Prep Question No 6

You have just been assigned to lead a project that is already underway. The objective is to develop a web application that tracks versions of computer code. At this time, the manage team process is being performed. In doing so, which of the following activities might be completed?

Option A : Arranging for key project team members to be at the same site near critical milestones

Option B : Providing constructive feedback to team members. 

Option C : Ensuring that assigned resources are available as originally planned. 

Option D : Working with functional managers to assign the appropriate resources to project work.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Providing constructive feedback to team members. 

PMP Exam Question No 7

A project has been funded by a foreign country to install several water pumps in Sub-Saharan Africa. The goal is to increase the availability of clean water. During the project, the team spends time documenting the procurement method and identifying potential sellers. Which of the following is not an output from that process?

Option A : Source Selection Criteria 

Option B : Bid Documents 

Option C : Agreements 

Option D : Independent Cost Estimates

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Agreements

PMP Exam Sample Question No 8

Which of the following is not true about adaptive life cycles?

Option A : Deliveries, which include subsets of the overall product, occur frequently 

Option B : Key stakeholders are involved at specific milestones 

Option C : Change is incorporated in real-time during project delivery 

Option D : It is designed to be responsive to high levels of change

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Key stakeholders are involved at specific milestones 

PMP Exam Practice Question No 9

All of the following are true about fixed price incentive fee (FPIF) contracts except:

Option A : Incentives are awarded typically for meeting cost, schedule, or performance targets. 

Option B : The price is set at the start of the contract. 

Option C : Bonuses can be given if certain predetermined objectives are achieved. 

Option D : The seller is reimbursed for all allowable expenses.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The seller is reimbursed for all allowable expenses.

PMP Certification Exam Question No 10

A project manager is working with a team to design a new video game. At this point, she needs to determine whether or not independent estimates will be needed prior to requesting and purchasing services from vendors that will support the project. Which document should be reviewed to find this information?

Option A : Cost Management Plan 

Option B : Procurement Management Plan 

Option C : Cost Baseline 

Option D : Procurement Documents

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Procurement Management Plan 

PMP Certification Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply