Hi PMP aspirants, welcome to AKVTutorials. Looking for a curated collection of PMP Project Management Professional practice questions to enhance your exam readiness? Revolutionize your approach to PMP preparation with our Practice Questions—your secret weapon for conquering the Project Management Professional exam. In this article, you will get Agile Questions In PMP Mock Test Exam Paper 56. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
A project manager is working with a team to make several adjustments to a manufacturing process to meet new legal requirements. At this point, she needs to identify who on the project is authorized to release confidential messages. Which document should be reviewed to find this information?
Option A : Project Charter
Option B : Stakeholder Engagement Plan
Option C : Stakeholder Register
Option D : Communications Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Communications Management Plan
PMP Mock Test Question No 2
At this point on your project, you are in the process of performing qualitative risks analysis. Which of the following are tools or techniques of that process?
Option A : Interviews, Risk Probability & Impact Assessment, SWOT Analysis
Option B : Hierarchical Charts, Meetings, Contingent Response Strategies
Option C : Sensitivity Analysis, Decision Tree Analysis, Influence Diagrams
Option D : Risk Data Quality Assessment, Risk Categorization, Meetings
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Risk Data Quality Assessment, Risk Categorization, Meetings
PMP Practice Exam Question No 3
A project manager is leading an effort to build a lab that will be used to conduct medical research. During the project, she uses earned value analysis and determines that the CPI is 1.35 and the SPI is 1.25. What does this indicate?
Option A : The project is under budget and ahead of schedule.
Option B : The project is over budget and behind schedule.
Option C : The project is under budget and behind schedule.
Option D : The project is over budget and ahead of schedule
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
The project is under budget and ahead of schedule.
PMP Mock Exam Question No 4
On your project, 14 stakeholders have been identified. Based on this information, how many possible communication channels exist?
Option A : 98
Option B : 27
Option C : 196
Option D : 91
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
91
Project Management Professional Question No 5
On a project to digitize a paper-based filing system at a law firm, the team spends time seeking authorization to begin expending resources to complete the project. In this case, what process is being performed?
Option A : Acquire Resources
Option B : Identify Stakeholders
Option C : Develop Project Charter
Option D : Develop Project Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Develop Project Charter
PMP Certification Prep Question No 6
A project to implement enterprise resource planning software within a government agency is underway. Currently, the team is performing the control scope process. In doing so, which of the following activities might they complete?
Option A : Determining which of the documented requirements will be completed as part of the project.
Option B : Reviewing verified deliverables with the sponsor to confirm they were completed properly.
Option C : Evaluating the completion of project deliverables and preventing scope creep.
Option D : Splitting the work of the project to make it easier to manage and monitor.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Evaluating the completion of project deliverables and preventing scope creep.
PMP Exam Question No 7
A project is underway to produce a new music album for a rock band known around the world. During the project, the team spends time putting risk response plans into effect. In this case, what process is being performed?
Option A : Plan Risks Responses
Option B : Identify Risks
Option C : Monitor Risks
Option D : Implement Risk Responses
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Initiate the change request process.
PMP Exam Sample Question No 8
Your project team has been tasked with closing a major shopping mall in suburban Chicago that has lost significant business. At this time, the team is performing quantitative risk analysis. In doing so, which of the following activities might they perform?
Option A : Performing sensitivity analysis and displaying the results using a tornado diagram.
Option B : Conducting root cause analysis to pinpoint the source of a problem.
Option C : Identifying high priority risks by evaluating their probability and impact.
Option D : Exploring options for addressing risks that have been previously identified.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Performing sensitivity analysis and displaying the results using a tornado diagram.
PMP Exam Practice Question No 9
A project manager is working with a team to construct a new soccer stadium. Early in the project, she would like to see a high-level explanation of the purpose and objectives for the project. Which document should be reviewed to find this information?
Option A : Project Charter
Option B : Statement of Work
Option C : Work Breakdown Structure
Option D : Benefits Management Plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Project Charter
PMP Certification Exam Question No 10
At this point on your project, you are in the process of estimating the labor and physical resources that are needed to complete the work. Which of the following are outputs of that process?
Option A : Assumption Log, Project Schedule Network Diagrams, Resource Requirements
Option B : Resource Breakdown Structure, Schedule Baseline, Duration Estimates
Option C : Milestone List, Resource Requirements, Duration Estimates
Option D : Resource Requirements, Basis of Estimates, Resource Breakdown Structure
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Statement of work (SOW)