Hi PMP aspirants, welcome to AKVTutorials. Are you exploring PMP practice mock tests to sharpen your knowledge and boost your confidence? Fuel your PMP ambitions with our Practice Questions—an invaluable resource for navigating the Project Management Professional certification landscape. In this article, you will get Actual PMP Exam Questions Test Paper 55. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A healthcare company that makes equipment for spinal surgeries has decided to setup a PMO in hopes of improving the delivery of their research and development projects. The PMO will provides templates, tools, and coaching to aid projects mangers and simplify their work. Which type of PMO does this represent?

Option A : Supportive 

Option B : Controlling 

Option C : Directive 

Option D : Strategic

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Supportive

PMP Mock Test Question No 2

A project manager at a company that makes hiking equipment speaks with key stakeholders about projected growth in the sporting goods market. This activity would fit into which of the following skills set in the PMI Talent Triangle®?

Option A : Strategic and Business Management 

Option B : Technical Project Management 

Option C : Leadership

Option D : Market Assessment

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Strategic and Business Management 

PMP Practice Exam Question No 3

A project to lead a joint military training exercise with two other countries is underway. Currently, the team is performing the perform integrated change control process. In doing so, which of the following activities might they complete?

Option A : Evaluating project performance to determine if any preventive or corrective action is needed. 

Option B : Releasing and reallocating project resources and archiving project information. 

Option C : Reviewing proposed adjustments to project baselines and the supporting cost estimates. 

Option D : Evaluating the completion of project deliverables and preventing scope creep.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Reviewing proposed adjustments to project baselines and the supporting cost estimates. 

PMP Mock Exam Question No 4

In regards to agile projects, which of the following is not true?

Option A : If the scope is not yet fully defined, projects may not benefit from detailed cost calculations 

Option B : Detailed estimates are used for short-term planning horizons 

Option C : Close collaboration among team members is critical

Option D : Infrequent checkpoints are valued and prevent distraction

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Close collaboration among team members is critical

Project Management Professional Question No 5

On a project to design a new self-driving vehicle, the team spends time developing a detailed project and product description that will help set boundaries for the project. What is an input to that particular process?

Option A : Stakeholder Register 

Option B : Requirements Documentation

Option C : Project Scope Statement 

Option D : Alternatives Analysis

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Requirements Documentation

PMP Certification Prep Question No 6

You were recently hired by a pharmaceutical company to lead a high priority project. Before moving forward, you understand that the structure of the organization will influence your work – whether for good or bad. The pharmaceutical company is considered a functional organization. All of the following are true about that organizational type except:

Option A : Functional managers hold more authority than project managers 

Option B : Resource availability for projects is low

Option C : Project managers control more of the budgets than functional managers 

Option D : Project managers have roles that are part-time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project managers control more of the budgets than functional managers 

PMP Exam Question No 7

During planning phases, projects are baselined. After that, any proposed changes to those plans need to be carefully controlled and considered in the context of the overall project. This process is referred to as integrated change control. All of the following is true about this process except:

Option A : It is conducted throughout the life of a project. 

Option B : The approver of changes will be identified in the project management plan. 

Option C : Change requests should include any impact to cost and schedule. 

Option D : Baselines are revised prior to the submission of change requests.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Baselines are revised prior to the submission of change requests.

PMP Exam Sample Question No 8

A project is underway to upgrade an oil pipeline in order to meet a new legal requirement. During that project, the team spends time identifying relationships (or order) of project activities. What is a tool or technique that may be needed to perform this process?

Option A : Rolling Wave Planning

Option B : Project Management Information System

Option C : Meetings 

Option D : Parametric Estimating

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Project Management Information System

PMP Exam Practice Question No 9

At a recent meeting on a project to rebrand a national restaurant chain, you discuss progress being made on identifying stakeholders. What is an activity that could be performed during that process?

Option A : Preparing a stakeholder engagement assessment matrix. 

Option B : Identifying the information needs of stakeholders. 

Option C : Conducting surveys of stakeholders to see if communication needs have been met. 

Option D : Classifying stakeholders based on their level of authority.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Classifying stakeholders based on their level of authority.

PMP Certification Exam Question No 10

You are soliciting advice from several experts, who have worked on similar projects, as you prepare the work breakdown structure (WBS). All of the following are purposes of this document except:

Option A : Articulate the components of work that will satisfy project objectives. 

Option B : Subdivide the project work into more manageable components. 

Option C : Provides detailed information, such as codes of account, about WBS components. 

Option D : Provide a hierarchical structure for assigning costs to work packages.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Provides detailed information, such as codes of account, about WBS components. 

PMP Practice Exam Questions And Answers Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply