Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and in search of practice questions that emphasize the importance of quality management in project delivery? Fast-track your PMP success with our Practice Questions—a comprehensive guide to mastering Project Management Professional concepts. In this article, you will get PMP Certification Exam Test Questions Paper 130 Explanation. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
Administrative closure to be done
Option A : at the end of the project D
Option B : at the end of each phase
Option C : before starting a new phase
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and b
PMP Exam Preparation Test Question No 2
Following documents will be reviewed as a part of administration closure
Option A : documentation of product of the project D .
Option B : performance measurement documentation
Option C : project records
Option D : all of the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all of the above
PMP Exam Sample Exam Question No 3
The outputs from administration closure includes
Option A : project archives
Option B : formal acceptance
Option C : project termination
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
project archives
PMP Certification Exam Question No 4
Formal acceptance should be done through[6]
Option A : verbal agreement between project sponsor and customer
Option B : documentation that the client has accepted the product of the project
Option C : documentation that the project sponsor has accepted the project results
Option D : b or c
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
define the relationship between the product being created and the business need.
Free PMP Practice Exam Question No 5
While archiving the project records specific attention must be paid if[7]
Option A : contractual agreements are involved
Option B : significant procurements involving key financial records are involved
Option C : project are terminated
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and b
Best PMP Exam Practice Question No 6
A Project Manager is most likely to have the strongest influence in an organization that is:
Option A : Balanced Matrix
Option B : Functional
Option C : Projectized
Option D : Strong Matrix
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Projectized
Free PMP Exam Prep Question No 7
Project Management processes are:
Option A : A series of actions bringing about a result
Option B : Concerned with describing and organizing the work of the project
Option C : Concerned with specifying and creating the product
Option D : Broken into core and non-core processes
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Concerned with describing and organizing the work of the project
Latest PMP Exam Question No 8
Executing processes are concerned with:
Option A : Recognizing that a project or phase should begin
Option B : Coordinating people and other resources to carry out the plan
Option C : Devising and maintaining a workable method to accomplish the business need that the project was undertaken to address
Option D : Ensuring that the project objectives are met by monitoring and measuring progress and taking corrective action when necessary
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Coordinating people and other resources to carry out the plan
PMI PMP Exam Practice Question No 9
Controlling processes are concerned with:
Option A : Coordinating people and other resources to carry out the plan
Option B : Recognizing that a project or phase should begin
Option C : Ensuring that the project objectives are met by monitoring and measuring progress and taking corrective action when necessary
Option D : Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Ensuring that the project objectives are met by monitoring and measuring progress and taking corrective action when necessary
PMP Certification Exam Agile Question No 10
A complex project will fit best in what type of organization?
Option A : Functional
Option B : Cross-functional
Option C : Matrix
Option D : Balanced
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Balanced