Hi PMP aspirants, welcome to AKVTutorials. Ready to evaluate your knowledge of PMP concepts through scenario-based practice questions that mirror real-world project scenarios? Engage stakeholders effectively using our practice questions, addressing communication and stakeholder management nuances crucial for PMP success. In this article, you will get PMP Certification Exam Free Questions Paper 126 Answer Keys. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
In making an investment in a project, investors require compensation for which of the following?
Option A : The risk-free rate of return plus a risk premium plus a premium for inflation.
Option B : Sacrifice of immediate use of cash for consumption or other investments, possibility of inflation and risk.
Option C : Payback period in years x investment x (1 + discount rate)periods.
Option D : Inflation and depreciation.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Sacrifice of immediate use of cash for consumption or other investments, possibility of inflation and risk.
PMP Exam Preparation Test Question No 2
A summary activity in a network logic diagram is often referred to as a :
Option A : Hammock.
Option B : Dangler.
Option C : Milestone.
Option D : Subtask.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Hammock.
PMP Exam Sample Exam Question No 3
Project communication management includes the process required to ensure
Option A : timely and appropriate generation collection and dissemination of project information
Option B : storage and ultimate disposition of project information
Option C : critical links among people, ideas and information
Option D : all the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all the above
PMP Certification Exam Question No 4
Communication planning in a project determines
Option A : who needs what information
Option B : when will they need it and how will it be given
Option C : key performance reports to be circulated among stake holders
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and b
Free PMP Practice Exam Question No 5
Following are some of the tools and techniques in project communication management except
Option A : stakeholder analysis
Option B : earned value analysis
Option C : presentation techniques
Option D : performance reviews
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
presentation techniques
Best PMP Exam Practice Question No 6
On most of the projects the majority of communication planning is done as part of
Option A : project initiation
Option B : project planning
Option C : project execution
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
project planning
Free PMP Exam Prep Question No 7
The results of communication planning will be reviewed and revised as needed
Option A : project execution phase
Option B : project controlling phase
Option C : through out the project
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
through out the project
Latest PMP Exam Question No 8
Project resources must be expanded on communication only when
Option A : the information contributes to project success
Option B : lack of communication leads to failure of the project
Option C : the project stakeholders ask for information
Option D : a and b
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
a and b
PMI PMP Exam Practice Question No 9
Information typically required to determine project communication requirements includes
Option A : project organization and stakeholders responsibility relationship
Option B : disciplines, departments and specialties involved in the project
Option C : external information needs
Option D : all the above
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
all the above
PMP Certification Exam Agile Question No 10
Communication technology and communication requirements are
Option A : input to communication planning
Option B : outputs from communication planning
Option C : inputs for information distribution
Option D : inputs for information distribution
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
input to communication planning