Hi PMP aspirants, welcome to AKVTutorials. In the midst of PMP exam preparation, are you on the hunt for practice questions that cover both predictive and agile methodologies? Secure your PMP success by mastering risk management with our practice questions, focusing on this critical aspect of Project Management Professional certification. In this article, you will get PMI PMP Exam Questions Test Paper 122. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
Variance analysis , trend analysis and earned value analysis are tools and technique used for :
Option A : Information distribution
Option B : Administrative closure.
Option C : Quality assurance.
Option D : Performance reporting
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Performance reporting
PMP Exam Preparation Test Question No 2
Status meeting are held to:
Option A : have team members report on what they are doing?
Option B : exchange information about the project.
Option C : issue work authorizations.
Option D : confirm the accuracy of the cost submitted by the team.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
exchange information about the project.
PMP Exam Sample Exam Question No 3
Given the following sample of data : 40,20,20,50,70, and 75: What is the mode?
Option A : 36
Option B : 20
Option C : 50
Option D : 70
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
50
PMP Certification Exam Question No 4
As part of project to establish a large vegetable growing operation for a food processing plant ,You are required to do several soil samples at the designated agricultural site. At the next PM meeting you must present your findings from the soil samples. You have received from the testing lab, the results from almost 80% of the soil samples but there is approximately 20% of the sample results still missing. Since you actually did a few more soil samples than was initially required , You will:
Option A : Prepare a report based on the information you did receive
Option B : Inform the customer that you need more time to redo the missing soil samples.
Option C : Prepare a report based on the information you did receive but included a statement regarding the missing soil samples.
Option D : Ask management to postpone the project meeting so you have time to redo the missing soil samples.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Prepare a report based on the information you did receive but included a statement regarding the missing soil samples.
Free PMP Practice Exam Question No 5
In a software company a large number of simultaneously performed projects utilize the same groups of human and other resources. What is the term commonly used for this situation?
Option A : Concurrent engineering.
Option B : Resource over-allocation.
Option C : Resource pooling.
Option D : Program management.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Resource pooling.
Best PMP Exam Practice Question No 6
What does the acronym RAM commonly stand for in project management?
Option A : Responsibility Assignment Matrix.
Option B : Remotely Applied Measurements.
Option C : Risk Aware Management.
Option D : Randomly Accessible Material.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Responsibility Assignment Matrix.
Free PMP Exam Prep Question No 7
A precontract agreement that establishes the intent of a party to buy products or services is called a :
Option A : Seller initial response.
Option B : Seller immediate response.
Option C : Letter of intent.
Option D : Letter of credit.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Letter of intent.
Latest PMP Exam Question No 8
What should not be part of a risk management plan?
Option A : Roles and responsibilities for handling risks.
Option B : Timing of risk management activities.
Option C : The managerial approach towards risk.
Option D : Individual risks.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
The managerial approach towards risk.
PMI PMP Exam Practice Question No 9
A project manager performs Earned Value Analysis and finds the following results: EV: 250,000; PV: 200,000; AC 275,000 BAC is 500,000. What is right?
Option A : EAC = 400,000.
Option B : EAC = 550,000.
Option C : BTC = 400,000.
Option D : ETC = 75,000.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The managerial approach towards risk.
PMP Certification Exam Agile Question No 10
The construction of a residential home will cost a certain amount per square foot of living space. This is an example of what type of estimating?
Option A : Analogous estimating.
Option B : Bottom-up estimating.
Option C : Top-down estimating.
Option D : Parametric modeling.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Parametric modeling.