Hi PMP aspirants, welcome to AKVTutorials. Looking for PMP practice questions that cover the breadth and depth of Project Management Professional topics? Ignite your PMP aspirations with our Practice Questions—your gateway to mastering Project Management Professional principles. In this article, you will get Free PMP Exam Questions Test 113 Answers Keys Explanation. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.
PMP Exam Practice Questions
PMP Exam Prep Practice Test Question No 1
When the expected cash flow S-curve is above the cost performance baseline?
Option A : no corrective action is required since the baseline cost exceeds the expected costs.
Option B : corrective action is required since the baseline cost exceeds the expected costs.
Option C : corrective action is required since the expected cost exceeds the expected costs.
Option D : no corrective action is required since the expected cost exceeds the expected costs
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
no corrective action is required since the expected cost exceeds the expected costs
PMP Exam Preparation Test Question No 2
In general the following statements are true about a project , except when it is:
Option A :Units of currency.
Option B : has a limited duration- beginning and end.
Option C : involves the coordinated undertaking of interrelated activities.
Option D : is repeatable.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
is repeatable.
PMP Exam Sample Exam Question No 3
The graphic displays of results over time ,of a process used to determine the states are called:
Option A : Fishbone diagram.
Option B : control chats.
Option C : Pareto chats
Option D : Histograms.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
control chats.
PMP Certification Exam Question No 4
Formal acceptance of a project can be described when:
Option A : The project is almost complete.
Option B : Customer signoff the product is documented .
Option C : Final payment is made
Option D : Contract documentation is approved
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Customer signoff the product is documented .
Free PMP Practice Exam Question No 5
From the “view exhibit” button , how many days of free float does activity H have?
Option A : 0
Option B : 8
Option C : 2
Option D : 12
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
8
Best PMP Exam Practice Question No 6
Which of the represents the different channels of communication?
Option A : Problem solving and compromise.
Option B : Compromise and confrontation.
Option C : Upward, downward, and lateral.
Option D : memos, status reports , and rumors.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Upward, downward, and lateral.
Free PMP Exam Prep Question No 7
One of the 9 “ilities” or attributes of qualities is “Availability”. Availability means the probability of a product being capable of performing a required function under the specified condition when called upon. The key parts to availability are:
Option A : reliability and maintainability
Option B : reliability and flexibility.
Option C : maintainability and flexibility.
Option D : producibility and operability.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
reliability and maintainability
Latest PMP Exam Question No 8
Which is not a true statement about the 5 project process group?
Option A : Concerned with describing and organizing the work of the project.
Option B : Linked by the product they produce.
Option C : Concerned with specifying and creating the product of the project.
Option D : Executed of the project as a whole , and for each phase within the PLC
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Concerned with specifying and creating the product of the project.
PMI PMP Exam Practice Question No 9
Every culture is governed by five fundamental dimensions. Which of the following is not one of those dimensions?
Option A : Information flow.
Option B : language.
Option C : Sense of time.
Option D : Sense of ownership.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Sense of ownership.
PMP Certification Exam Agile Question No 10
Project managers working in successful ,projectized environments believe that spend what percentage of their time on communications?
Option A : 30-45%
Option B : 45-60%
Option C : 60-75%
Option D : 75-90%
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
75-90%