PMP Mock Test 88 Exam Questions Paper

Hi PMP aspirants, welcome to AKVTutorials. Are you exploring PMP Project Management Professional practice questions that focus on the application of earned value management for performance measurement? Engage stakeholders effectively using our practice questions, addressing communication and stakeholder management nuances crucial for PMP success. In this article, you will get PMP Mock Test 88 Exam Questions Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

 What is the Delphi technique?

Option A : A simulation technique.

Option B : A mathematical analysis.

Option C : A constrained optimization method.

Option D : A consensus technique.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

A consensus technique.

PMP Mock Test Question No 2

What is the process of splitting a deliverable into smaller more manageable parts called?

Option A : Scope definition.

Option B : Decomposition.

Option C : Activity definition.

Option D : Activity lists.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Scope definition.

PMP Practice Exam Question No 3

The WBS helps the team of FOCUS! It is an excellent tool for communications and the basic for developing realistic estimates. You can best describe a WBS as a tool for the tracking of the:

Option A : the schedule

Option B : assigned resources

Option C : project costs.

Option D : project scope

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

project scope

PMP Mock Exam Question No 4

The WBS is

Option A : a description of the product component and subcomponents.

Option B : a breakdown of the project reporting structure.

Option C : a structure that defines the scope baseline for the project.

Option D : a structure that defines work assignments by organizations.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

a structure that defines the scope baseline for the project.

Project Management Professional Question No 5

You and several of your key team leader are really struggling with estimating the overall cost of the project. The most probable cause for this estimating difficulty can be contributed to:

Option A : initial poor scope definition

Option B : lack of required resources.

Option C : insufficient funds.

Option D : problems with the overall schedule.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

initial poor scope definition

PMP Certification Prep Question No 6

Which statement is true?

Option A : ideally one should optimize the schedule once.

Option B : creating a Gantt chat should only be done once when bidding on the project.

Option C : Ideally the base line should only be done once in a project.

Option D : ideally constraint dates should be done once in a project.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Ideally the base line should only be done once in a project.

PMP Exam Question No 7

Which factors should you consider when adding a resource to your project team?

Option A : The impact the resource will have on the cost of the system

Option B : The impact the resource will have on the duration of the system

Option C : The impact the resource will have on the histogram.

Option D : Whether the resource is available, and if it will have impact on the cost and duration of the system

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Ideally the base line should only be done once in a project.

PMP Exam Sample Question No 8

The Delphi method is best suited for:

Option A : Decision-making

Option B : Simulation models

Option C : Quality improvement

Option D : Team discussions

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Decision-making

PMP Exam Practice Question No 9

You are on the project selection team and must decide on only one project to approve. Of the following 2 possible project which would you select and why?

Option A : project Toronto because because the NPV is the highest number

Option B : project Calgary because the payback period is shorter than the project Toronto.

Option C : Can not be determined based on the information provided.

Option D : project Calgary because the NPV is positive and the payback period is sooner than Toronto.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Can not be determined based on the information provided.

PMP Certification Exam Question No 10

 There are two types of decision model, comparative and constrained that can be used for the project selection during the initiation process. Of the following decision model examples, which one are categorized as benefit measurement or scoring/ rating models?

Option A : Criteria profiling weighted factor, q shorting, Delphi technique, logical frame work analysis, and linear program programming.

Option B : logical frame work analysis and linear program programming.

Option C : logical frame work analysis, criteria profiling, weighted factor, Q shorting and Delphi technique.

Option D : Criteria profiling, weighted factor, Q shorting, and Delphi technique?

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Criteria profiling, weighted factor, Q shorting, and Delphi technique?

PMP Exam Practice Test Questions And Solutions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply