PMP Exam Test Questions Free Test Paper 86

Hi PMP aspirants, welcome to AKVTutorials. Ready to challenge your risk management skills with PMP practice questions that assess your ability to identify, analyze, and respond to project risks? Navigate ethical considerations confidently with our PMP practice questions, emphasizing professional responsibility and integrity. In this article, you will get PMP Exam Test Questions Free Test Paper 86. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Your developer has provided u with an estimate based on the “cost per line of code”.What type of estimate did the developer use to provide this information?

Option A : Parametric estimating.

Option B : Bottom-up- estimating.

Option C : Analogues estimating.

Option D : PERTestmating 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Parametric estimating.

PMP Mock Test Question No 2

A definitive estimate is:

Option A : Top-down estimating.

Option B : Created during initiation.

Option C : Within a range of -10% to +25% of actual.

Option D : The most expensive to create.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The most expensive to create.

PMP Practice Exam Question No 3

all of the following are inputs to the cross-budgeting process expect?

Option A : cost estimate.

Option B : project schedule.

Option C : risk management plan.

Option D : Deactivate duration estimates.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Deactivate duration estimates.

PMP Mock Exam Question No 4

Analogues estimating is a tool technique used in both Time and Cost management process. What is the best description of how analogues estimating is performed?

Option A : by-buttom-up estimating techniques.

Option B : obtaining management option’s of the estimate of each task.

Option C : by-top-down estimating techniques.

Option D : based on historical costs.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

by-top-down estimating techniques.

Project Management Professional Question No 5

Cost budgeting is defined as

Option A : the estimated total cost of the Project when done.

Option B : allocating the cost estimates to the individual work items.

Option C : developing estimates of the cost of the resources needed to complete project activities.

Option D : the sum of the approved cost estimates

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

allocating the cost estimates to the individual work items

PMP Certification Prep Question No 6

Due to recent company downsizing u can only authorize 1 of the 2 projects u really planed to complete this year. You have decided to select the project with the NPV of $95k and proceed to cancel the other project which had an NPV of $37k what are the opportunity costs associated with this new decision?

Option A : $37k

Option B : $95k

Option C : $123k

Option D : $58k

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

$37k

PMP Exam Question No 7

Analogues estimating is a form of

Option A : earned value.

Option B : expert judgment.

Option C : cost planning

Option D : parametric modeling.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

expert judgment

PMP Exam Sample Question No 8

Two projects have exactly the same pay back period but project A has a smaller IRR than project B.

Option A : project A.

Option B : project B

Option C : there is no difference

Option D : there is not enough information available

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

project B

PMP Exam Practice Question No 9

 The expected accuracy level of estimates during the initiation phase of project should be:

Option A : -25% to +75%

Option B : -10% to +25%

Option C : -35%to +75%

Option D : -10%to +10%

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

-25% to +75%

PMP Certification Exam Question No 10

Analogues estimating is most accurate when:

Option A : previous projects are similar in fact not just appearance.

Option B : there is a relationship between the cost being estimated and known parameter.

Option C : the historical information used to develop the model is accurate.

Option D : work items are very small.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

previous projects are similar in fact not just appearance

New PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply