Hi PMP aspirants, welcome to AKVTutorials. Ready to challenge your risk management skills with PMP practice questions that assess your ability to identify, analyze, and respond to project risks? Navigate ethical considerations confidently with our PMP practice questions, emphasizing professional responsibility and integrity. In this article, you will get PMP Exam Test Questions Free Test Paper 86. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Your developer has provided u with an estimate based on the “cost per line of code”.What type of estimate did the developer use to provide this information?
Option A : Parametric estimating.
Option B : Bottom-up- estimating.
Option C : Analogues estimating.
Option D : PERTestmating
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Parametric estimating.
PMP Mock Test Question No 2
A definitive estimate is:
Option A : Top-down estimating.
Option B : Created during initiation.
Option C : Within a range of -10% to +25% of actual.
Option D : The most expensive to create.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The most expensive to create.
PMP Practice Exam Question No 3
all of the following are inputs to the cross-budgeting process expect?
Option A : cost estimate.
Option B : project schedule.
Option C : risk management plan.
Option D : Deactivate duration estimates.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Deactivate duration estimates.
PMP Mock Exam Question No 4
Analogues estimating is a tool technique used in both Time and Cost management process. What is the best description of how analogues estimating is performed?
Option A : by-buttom-up estimating techniques.
Option B : obtaining management option’s of the estimate of each task.
Option C : by-top-down estimating techniques.
Option D : based on historical costs.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
by-top-down estimating techniques.
Project Management Professional Question No 5
Cost budgeting is defined as
Option A : the estimated total cost of the Project when done.
Option B : allocating the cost estimates to the individual work items.
Option C : developing estimates of the cost of the resources needed to complete project activities.
Option D : the sum of the approved cost estimates
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
allocating the cost estimates to the individual work items
PMP Certification Prep Question No 6
Due to recent company downsizing u can only authorize 1 of the 2 projects u really planed to complete this year. You have decided to select the project with the NPV of $95k and proceed to cancel the other project which had an NPV of $37k what are the opportunity costs associated with this new decision?
Option A : $37k
Option B : $95k
Option C : $123k
Option D : $58k
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
$37k
PMP Exam Question No 7
Analogues estimating is a form of
Option A : earned value.
Option B : expert judgment.
Option C : cost planning
Option D : parametric modeling.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
expert judgment
PMP Exam Sample Question No 8
Two projects have exactly the same pay back period but project A has a smaller IRR than project B.
Option A : project A.
Option B : project B
Option C : there is no difference
Option D : there is not enough information available
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
project B
PMP Exam Practice Question No 9
The expected accuracy level of estimates during the initiation phase of project should be:
Option A : -25% to +75%
Option B : -10% to +25%
Option C : -35%to +75%
Option D : -10%to +10%
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
-25% to +75%
PMP Certification Exam Question No 10
Analogues estimating is most accurate when:
Option A : previous projects are similar in fact not just appearance.
Option B : there is a relationship between the cost being estimated and known parameter.
Option C : the historical information used to develop the model is accurate.
Option D : work items are very small.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
previous projects are similar in fact not just appearance