Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want practice questions that align with the agile mindset and principles? Propel yourself toward PMP success by practicing with our updated questions, aligning with the latest changes in the Project Management Professional exam content. In this article, you will get PMP Project Management Professional Certification Exam Test 83 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Which of the following is not a type of baseline from which to measure change?
Option A : Project plan
Option B : WBS
Option C : Operational definitions
Option D : Project schedule
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Operational definitions
PMP Mock Test Question No 2
There are three outputs that are common to scope, schedule and cost control processes. Which of the following is not a common output to these control processes?
Option A : Baseline updates/changes
Option B : Lessons learned
Option C : Corrective action
Option D : Process adjustments
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Process adjustments
PMP Practice Exam Question No 3
Performance reports are an input to overall change control. Which of the following statements is not necessarily true about performance reports?
Option A : They provide information on past project performance
Option B : They provide information on current status
Option C : They may alert the team to potential future problems
Option D : They are the outcome of project reviews
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
They are the outcome of project reviews
PMP Mock Exam Question No 4
You are continually faced with tasks coming in late because your resources are being pulled off to handle other “urgent” situatins. You have set up a conference with several of the managers who have been doing this on a regular basis. What technique might you use to alleviate the current situation?
Option A : Forcing
Option B : Problem solving
Option C : Smoothing
Option D : Ignoring
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Problem solving
Project Management Professional Question No 5
In a team meeting, two of the managers start a discussion that escalates into an argument. In order to restore peace to the meeting you point out the part of the conflict that they both agree to and using friendly tones try to defuse the current situation. This is an example of what type of conflict management?
Option A : Smoothing
Option B : Problem solving
Option C : Withdrawal
Option D : Compromising
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Smoothing
PMP Certification Prep Question No 6
A WBS provides a framework from which all of the following can be done except:
Option A : All tasks to be performed can be identified and resources allocated to them
Option B : Once resource levels have been allocated to tasks, estimates of task duration can be made
Option C : A network diagram, illustrating task dependencies, can be constructed
Option D : All cost and resource allocations can be totaled to develop the overall project budget
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
A network diagram, illustrating task dependencies, can be constructed
PMP Exam Question No 7
A WBS provides a framework from which all of the following can be done except:
Option A : A network diagram, illustrating task dependencies, can be constructed
Option B : All cost and resource allocations can be totaled to develop the overall project budget.
Option C : Performance can be tracked against the identified cost, schedule, and resource allocations
Option D : Assignment of responsibility for each element can be made
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
A network diagram, illustrating task dependencies, can be constructed
PMP Exam Sample Question No 8
Part of being a project manager involves dealing with conflict. According to John Adams, Ph.D., there are five methods for dealing with conflict. Some of them are used for temporary fixes, some provide more permanent resolutions. Which of the following is used for temporary resolution?
Option A : Smoothing
Option B : Problem solving
Option C : Forcing
Option D : Compromising
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Smoothing
PMP Exam Practice Question No 9
A Work Breakdown Structure provides a framework from which all of the following can be done except:
Option A : Task durations can be used in developing a working schedule for the project
Option B : A network diagram, illustrating task dependencies, can be constructed
Option C : Performance can be tracked against the identified cost, schedule, and resource allocations
Option D : Assignment of responsibility for each element can be made
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
A network diagram, illustrating task dependencies, can be constructed
PMP Certification Exam Question No 10
Which of the following is least likely to be a source of conflict in a matrix environment?
Option A : Competing priorities between the project and functional manager
Option B : Competing for resources between the functional and project manager
Option C : Project team member working at a different site than the project manager
Option D : Ambiguous lines of authority between the functional and project manager
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Project team member working at a different site than the project manager