Hi PMP aspirants, welcome to AKVTutorials. Are you aiming for PMP success and need practice questions that align with the latest changes in the Project Management Professional exam content? Excel in schedule management and critical path analysis with our PMP Project Management Professional practice questions, vital for effective project planning. In this article, you will get PMP Exam Multiple Choice Questions Paper 74. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
As a project manager on a software development project you are accountable for maintaining the integrity of the performance measurement baselines. This includes making sure that approved changes to the schedule and cost are reflected in the project plan. However, you also make sure that only changes to the project scope affect the performance measurement baselines. This is an example of:
Option A : Scope change control
Option B : Overall change control
Option C : Performance measurement
Option D : Configuration management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Overall change control
PMP Mock Test Question No 2
You are a PM at a pharmaceutical company. You are the project manager in charge of the development of a new drug that will reduce the after effects of chemo-therapy. What is an assumption that you might have as part of your project plan?
Option A : The budget is $7,000,000
Option B : In order to meet the schedule you will have to fast track several of the processes
Option C : There will not be a cure for cancer in the next 5 years
Option D : You cant move to human testing until animal testing is complete
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
There will not be a cure for cancer in the next 5 years
PMP Practice Exam Question No 3
You are considering outsourcing some of the work on your project. Doing this will reduce the amount of time it takes to complete the milestone, and it will increase the budget. You should document your decision and the reasons for it in:
Option A : The schedule baseline
Option B : The cost baseline
Option C : The change management plan
Option D : The project plan
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The project plan
PMP Mock Exam Question No 4
You have just been given a new project and are creating the project plan. You are reviewing team member planning assumptions, information from similar projects and the identified constraints and assumptions. What tools will you utilize in order to complete the project plan?
Option A : Project planning methodology and project management information system
Option B : Project management skills and general management skills
Option C : Stakeholder skills and knowledge and organizational policies
Option D : Other planning outputs and project planning methodology
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Project planning methodology and project management information system
Project Management Professional Question No 5
At appropriate times during your project, you issue task orders that describe what work is to be done, who is to do it, and when it is to be done. This is an example of:
Option A : Project scheduling
Option B : A work authorization system
Option C : Project planning
Option D : Overall change control
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
A work authorization system
PMP Certification Prep Question No 6
The organizational design of a project is critical to its successful management. Which of the following is not one of the three basic factors influencing decisions about the design of a project organization?
Option A : Environmental forces
Option B : Strategic choices
Option C : Schedule constraints
Option D : Technological factors
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Schedule constraints
PMP Exam Question No 7
The degree to which written policies, procedures, rules, and job descriptions guide the behavior of personnel involved in projects is called:
Option A : Centralization
Option B : Complexity
Option C : Specialization
Option D : Formalization
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Formalization
PMP Exam Sample Question No 8
Which of the following is not an organizational policy consideration in formulating a project plan?
Option A : Regulatory compliance
Option B : Quality management
Option C : Personnel administration
Option D : Financial controls
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Regulatory compliance
PMP Exam Practice Question No 9
Which of the following activities is not a part of administrative closure?
Option A : Generating information
Option B : Filtering information
Option C : Gathering information
Option D : Disseminating information
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Filtering information
PMP Certification Exam Question No 10
Which of the following is not a tool or technique for overall change control?
Option A : Performance measurement
Option B : Configuration management
Option C : Work Authorization system
Option D : Project management information system
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Work Authorization system