Practice PMP Exam Questions Test 52 with Answer Explanation

Hi PMP aspirants, welcome to AKVTutorials. Seeking PMP practice questions to fine-tune your Project Management Professional skills? Ignite your PMP aspirations with our Practice Questions—your gateway to mastering Project Management Professional principles. In this article, you will get Practice PMP Exam Questions Test 52 with Answer Explanation. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A project manager is creating a procurement management plan for a project that involves implementing software that will be used to track and follow up on sales leads. Which of the following would not be included in that document?

Option A : The criteria that will be used when determining which vendor to select 

Option B : The roles and responsibilities related to the procurement 

Option C : An explanation of how vendor performance will be monitored and measured 

Option D : A list of pre-qualified sellers, if any

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

The criteria that will be used when determining which vendor to select 

PMP Mock Test Question No 2

Which of the following is true about scope management on agile projects?

Option A : Scope would only change when a change request is approved 

Option B : Scope is defined at the beginning of the project

Option C : Project scope includes the features and functions of the project 

Option D : Scope is approved at the start of each iteration

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project scope includes the features and functions of the project 

PMP Practice Exam Question No 3

At this point on your project, you are in the process of reviewing and approving change requests and then communicating those decisions to your stakeholders. Which of the following are inputs of that process?

Option A : Project Management Plan, Work Performance Reports, Change Requests 

Option B : Project Charter, Change Requests, Agreements 

Option C : Work Performance Reports, Work Performance Information, Project Documents 

Option D : Change Requests, Project Management Plan, Approved Changed Requests

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Change Requests, Project Management Plan, Approved Changed Requests

PMP Mock Exam Question No 4

All of the following are true about fixed price with economic price adjustment (FP-EPA) contracts except:

Option A : The price is set at the start of the contract. 

Option B : There may be price adjustments over time based on changes to certain financial indices. 

Option C : They are often used when a contract is several years in length. 

Option D : The duration and scope can be left open-ended.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

The price is set at the start of the contract. 

Project Management Professional Question No 5

A project manager is working with a team to automate several manufacturing steps at a tire production plant. At this point, she needs to understand what process should be used when the project team (or stakeholders) need to escalate concerns. Which document should be reviewed to find this information?

Option A : Risk Management Plan 

Option B : Stakeholder Register 

Option C : Communications Management Plan 

Option D : Stakeholder Engagement Plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project schedule

PMP Certification Prep Question No 6

A project to construct a bypass has the goal of easing traffic congestion near a large city. During the project, the team spends time communicating with their stakeholders and addressing their issues and concerns. In this scenario, what process is being performed?

Option A : Manage Stakeholder Engagement 

Option B : Monitor Stakeholder Engagement

Option C : Manage Communications 

Option D : Plan Stakeholder Engagement

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Monitor Stakeholder Engagement 

PMP Exam Question No 7

Your project team has been tasked with designing a new, more fuel-efficient truck. At this time, the team is implementing risk responses. In doing so, which of the following activities might they perform?

Option A : Exploring options for addressing risks that have been previously identified. 

Option B : Evaluating whether or not risks responses have been effective. 

Option C : Performing sensitivity analysis and displaying the results using a tornado diagram. 

Option D : Taking action to increase the likelihood that opportunities on the project occur.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Performing sensitivity analysis and displaying the results using a tornado diagram. 

PMP Exam Sample Question No 8

An issue will cause the project team to miss a critical milestone. The project manager realizes that this issue could have been avoided if the risk had been addressed earlier. What should the project manager do next?

Option A : Hold a meeting with the sponsor and key stakeholders to inform them of the issue.

Option B : Consult with the team and update the project management plan based on their inputs.

Option C : Create and submit a change request that includes a recommendation for corrective action.

Option D : Taking action to increase the likelihood that opportunities on the project occur.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Taking action to increase the likelihood that opportunities on the project occur.

PMP Exam Practice Question No 9

A project manager is preparing a cost management plan for a project that includes constructing a hanger for military aircrafts. Which of the following would not be included in that document?

Option A : An explanation of how earned value management will be used on the project

Option B : The format for reporting cost performance 

Option C : The degree of cost variance that would be acceptable before action needs to be taken 

Option D : The basis of estimates that provides additional detail and supports cost estimate

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The degree of cost variance that would be acceptable before action needs to be taken 

PMP Certification Exam Question No 10

On a given project; earned value (EV) is $30,000; actual cost (AC) is $35,000; and planned value (PV) is $28,000. What is the cost variance (CV)?

Option A : $2,000 

Option B : -$5,000 

Option C : $5,000 

Option D : -$2,000

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

-$2,000

PMP Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply