Hi PMP aspirants, welcome to AKVTutorials. Are you in search of high-quality PMP Project Management Professional practice questions to elevate your exam preparation? Navigate the path to PMP mastery with our Practice Questions—a game-changing resource for Project Management Professional hopefuls. In this article, you will get PMP Exam Mock Test 51 Questions And Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
On a given project; actual cost (AC) is $500,00; estimate at completion (EAC) is $800,000; and planned value is $850,000. What is estimate to completion (ETC)?
Option A : $50,000
Option B : $350,000
Option C : $300,000
Option D : $1,300,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
$300,000
PMP Mock Test Question No 2
On a project to setup a technology environment that allows a clothing business to process and gather insights from large volumes of customer data, the team spends time formally closing the project. What is an output from that process?
Option A : Agreements
Option B : Final Report
Option C : Procurement Documentation
Option D : Accepted Deliverables
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Final Report
PMP Practice Exam Question No 3
You have just been assigned to lead a project that is already underway. The objective is to design and test a new self-driving car. At this time, the develop team process is being performed. In doing so, which of the following activities might be completed?
Option A : Arranging for key project team members to be at the same site near critical milestones
Option B : Resolving a conflict between two team members.
Option C : Ensuring that assigned resources are available as originally planned.
Option D : Evaluating alternative resource options, such as renting or buying the needed equipment.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Arranging for key project team members to be at the same site near critical milestones
PMP Mock Exam Question No 4
A fast food restaurant chain is working on a project that involves piloting the use of drone technology to make local deliveries. During the project, the team spends time documenting how the schedule will be developed and controlled. What is an input to that particular process?
Option A : Activity List
Option B : Schedule Management Plan
Option C : Work Performance Data
Option D : Project Charter
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project Charter
Project Management Professional Question No 5
On a given project, the budget at completion (BAC) is $375,000. If your current estimate to completion (ETC) is $50,000 and estimate at completion (EAC) is $300,000; what is the variance at completion (VAC)?
Option A : $75,000
Option B : -$50,000
Option C : $25,000
Option D : -$25,000
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
$75,000
PMP Certification Prep Question No 6
A project is underway to launch a new service that allows users to share bikes on college campuses. During the project, the team spends time documenting how to estimate, acquire, and manage required project resources. What is an output from that process?
Option A : Resource Breakdown Structure
Option B : Project Team Assignments
Option C : Resource Requirements
Option D : Team Charter
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Team Charter
PMP Exam Question No 7
A project to develop a web-based inventory management system is ongoing. Currently, the team is performing the manage project knowledge process. In doing so, which of the following activities might they complete?
Option A : Evaluating project performance to determine if any preventive or corrective action is needed.
Option B : Archiving project information and releasing and reallocating project resources.
Option C : Allocating available resources (labor, material, and equipment) to activities in the project plan.
Option D : Considering positive and negative experiences from previous projects to increase the likelihood of success on the current project
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Considering positive and negative experiences from previous projects to increase the likelihood of success on the current project
PMP Exam Sample Question No 8
A project in Europe is underway to secure an electric grid to reduce the likelihood of a computer hack. During the project, the team spends time defining strategies and action to address project risks. Which of the following is not a tool or technique that may be needed to perform this process?
Option A : Contingent Response Strategies
Option B : Cost-Benefit Analysis
Option C : Decision Tree Analysis
Option D : Strategies for Threats
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Decision Tree Analysis.
PMP Exam Practice Question No 9
A project to renovate a hotel that was built in the 1970s is underway. Currently, the team is performing the control quality process. In doing so, which of the following activities might they complete?
Option A : Using audits to determine if activities on the project are conforming to organizational policies and then addresses gaps, if needed.
Option B : Testing project deliverables to identify errors or defects.
Option C : Using the six sigma methodology to identify process improvement opportunities.
Option D : Determining appropriate investments in prevention and appraisal costs in order to avoid quality failures
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Using audits to determine if activities on the project are conforming to organizational policies and then addresses gaps, if needed.
PMP Certification Exam Question No 10
You were recently hired by a gaming company to lead a strategic project. Before moving forward, you understand that the structure of the organization will influence your work. The gaming company is considered a projectized organization. Which of the following is not true about that organizational type?
Option A : Project managers hold more authority than functional managers
Option B : Resource availability for projects is high
Option C : Functional managers control less of the budgets than project managers
Option D : Project managers have roles that are part-time
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Project managers hold more authority than functional managers