Hi PMP aspirants, welcome to AKVTutorials. Seeking practice questions that assess your understanding of the Project Management Professional Code of Ethics and Professional Conduct? Uphold ethical standards with our PMP practice questions, aligning with the Project Management Professional Code of Ethics and Professional Conduct. In this article, you will get PMP Preparation Test Paper 48 Exam Questions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
Robert is determining the budget that will be required on a project to relocate a company’s operations to a new building. In doing so, he needs to evaluate whether or not funding will be available when expenses need to be paid. What should Robert use in this scenario?
Option A : Funding Limit Reconciliation
Option B : Historical Information Review
Option C : Financing
Option D : Cost Aggregation
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Funding Limit Reconciliation
PMP Mock Test Question No 2
A project manager is preparing a communications management plan for a project that includes constructing a new wing in a hospital that will focus on the treatment of cancer patients. Which of the following would not be included in that document?
Option A : The information needs of your stakeholders
Option B : A description of strategies that will be used to engage those impacted by the project
Option C : A list of resources that will be allocated to communication activities
Option D : The process that the project manager or stakeholders can use to escalate concerns
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
A description of strategies that will be used to engage those impacted by the project
PMP Practice Exam Question No 3
A project to relocate employees of an insurance company to a new office building has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. She also knows that significant changes to scope are likely and a fee will be paid if the vendors meet broad, subjective performance criteria. In this scenario, which type of contract should be utilized?
Option A : Cost Plus Fixed Fee (CFPP)
Option B : Cost Plus Incentive Fee (CPIF)
Option C : Cost Plus Award Fee (CPAF)
Option D : Fixed Price Incentive Fee (FPIF)
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Cost Plus Award Fee (CPAF)
PMP Mock Exam Question No 4
Maria is developing the schedule on a project that involves constructing an oil pipeline that will start in Canada and go through the mid-western United States. In order to complete that process, she needs to estimate the minimum project duration and amount of scheduling flexibility. Which tool or technique would accomplish this task?
Option A : Resource Optimization
Option B : Critical Path Method
Option C : Schedule Network Analysis
Option D : Schedule Compression
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Critical Path Method
Project Management Professional Question No 5
On a project to construct a toll road, which is expected to relieve traffic congestion and generate tax revenue, a team spends time documenting needs of their stakeholders. In this case, what process is being performed?
Option A : Define Scope
Option B : Plan Scope Management
Option C : Manage Stakeholder Engagement
Option D : Collect Requirements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Collect Requirements
PMP Certification Prep Question No 6
A technology company that specializes in creating software applications for dental offices is working on several multi-year projects for their customers. However, three new competitors, who are seeking to take away those customers, have recently entered the market. In this scenario, these marketplace conditions would be best classified as which of the following?
Option A : An enterprise environmental factor
Option B : An industry standard
Option C : An organizational process asset
Option D : A lesson that was learned
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
An enterprise environmental factor
PMP Exam Question No 7
A project manager is preparing a procurement management plan for a project that includes renovating a high school on a military base. Which of the following would not be included in that document?
Option A : The currency that will be used to pay vendors working on the project
Option B : A decision about whether or not certain scope will be completed by the project team or procured from outside vendors
Option C : The timetable of procurement activities
Option D : A statement on whether or not independent estimates will be needed prior to requesting and purchasing services from vendors
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
A decision about whether or not certain scope will be completed by the project team or procured from outside vendors
PMP Exam Sample Question No 8
As a project manager, you know that your projects are impacted by factors that are often outside of your control. Those factors could be internal or external to your organization, and they could have a positive or negative impact. Enterprise environmental factors are one such example. Which of the following is considered an enterprise environmental factor?
Option A : Political Climate
Option B : Organizational Communication Requirements
Option C : Human Resource Policies
Option D : Knowledge Bases
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Political Climate
PMP Exam Practice Question No 9
A project manager on a factory automation project prepares a memo for the sponsor. It explains that a key deliverable is behind schedule and that the expected completion date will be two weeks later than originally planned. This memo would be classified as which type of project information?
Option A : Work Performance Information
Option B : Work Performance Data
Option C : Enterprise Environmental Factors
Option D : Work Performance Reports
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Work Performance Reports
PMP Certification Exam Question No 10
A project manager at a company that services luxury cars attends a training to learn about earned value management. She believes it could be a valuable tool on her projects. This particular training would be considered a way to strengthen her skills in which of the following areas of the PMI Talent Triangle®?
Option A : Technical Project Management
Option B : Cost Control
Option C : Leadership
Option D : Strategic and Business Management
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Technical Project Management