Hi PMP aspirants, welcome to AKVTutorials. Looking for a comprehensive set of PMP Project Management Professional practice questions that address the evolving landscape of project management technology? Embrace technological advancements in project management with our practice questions, staying ahead in the evolving landscape of project management technology. In this article, you will get Sample PMP Exam Questions Practice Test 44. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.
PMP Exam Practice Questions
PMP Practice Test Question No 1
A project to build a new terminal at an airport is ongoing. Currently, the team is performing the plan cost management process. In doing so, which of the following activities might they complete?
Option A : Calculating contingency allowances that will be used to account for uncertainty.
Option B : Reviewing strategic funding options, such as the possibility of using debt to fund the project.
Option C : Documenting risks that were considered when cost projections were prepared.
Option D : Establishing the amount of management reserve, which will be used to pay for unexpected work
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Reviewing strategic funding options, such as the possibility of using debt to fund the project.
PMP Mock Test Question No 2
Francesco is collecting requirements on a project that involves building a courthouse for a local government. In order to do so, he wants to use a brainstorming method that involves voting on several requirements before they are further prioritized. Which tool or technique would accomplish this task?
Option A : Nominal Group Technique
Option B : Design of Experiments
Option C : Brainstorming
Option D : Focus Groups
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Nominal Group Technique
PMP Practice Exam Question No 3
A project manager is preparing a scope management plan for a project that includes upgrading three waste-water treatment plants. Which of the following would not be included in that document?
Option A : The steps for decomposing the scope into work packages
Option B : An explanation of how formal acceptance will be obtained on project deliverables
Option C : A listing of control accounts and planning packages
Option D : The process for creating the project scope statement
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
A listing of control accounts and planning packages
PMP Mock Exam Question No 4
A project manager is leading an effort to design a new 3D printer that accepts a broad range of filament types. During the project, she uses earned value analysis and determines that the CPI is 0.85 and the SPI is 1.25. What does this indicate?
Option A : The project is under budget and ahead of schedule.
Option B : The project is over budget and behind schedule.
Option C : The project is under budget and behind schedule.
Option D : The project is over budget and ahead of schedule.
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
The project is over budget and ahead of schedule.
Project Management Professional Question No 5
A project manager is working with a team to revitalize a city park. At this point, she needs to understand what currency will be used to pay vendors working on the project. Which document should be reviewed to find this information?
Option A : Procurement Management Plan
Option B : Cost Management Plan
Option C : Cost Baseline
Option D : Procurement Documents
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
Procurement Management Plan
PMP Certification Prep Question No 6
A department store is working on a project to close several locations. During the project, the team spends time decomposing project work into smaller components. What is an output from that process?
Option A : Project Scope Statement
Option B : Requirements Traceability Matrix
Option C : Scope Baseline
Option D : Lessons Learned Register
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: C
Scope Baseline
PMP Exam Question No 7
On your project, 12 stakeholders have been identified. Based on this information, how many possible communication channels exist?
Option A : 66
Option B : 132
Option C : 72
Option D : 6
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: A
66
PMP Exam Sample Question No 8
You are managing a project to develop the next version of a popular financial management tool for small businesses. At this point on your project, you are in the process of collecting requirements from stakeholders. One of the tools that will be used are surveys that will be sent to users. Which of the following are inputs of that process?
Option A : Assumption Log, Requirements Documentation, Project Charter
Option B : Project Scope Statement, Requirements Documentation, Quality Reports
Option C : Lessons Learned Register, Requirements Traceability Matrix, Risk Register
Option D : Project Charter, Lessons Learned Register, Agreements
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: D
Project Charter, Lessons Learned Register, Agreements
PMP Exam Practice Question No 9
On a project to landscape the grounds of a large university, the team spends time approximating the number of work periods needed to complete project activities. In this case, what process is being performed?
Option A : Develop Schedule
Option B : Estimate Activity Durations
Option C : Sequence Activities
Option D : Create WBS
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
Estimate Activity Durations
PMP Certification Exam Question No 10
A project manager is creating a stakeholder engagement plan for a project that involves redesigning the aluminum packaging for a popular soft drink. Which of the following would not be included in that document?
Option A : A formal or informal set of plans for engaging specific stakeholders
Option B : The classification of known stakeholders
Option C : Strategies for working productively with those who are impacted by the project
Option D : A list of tactics for dealing with demanding stakeholders
Show/Hide Answer
Answer Keys: YES
Explanation: No
Correct Answer: B
The classification of known stakeholders