Sample PMP Exam Questions Practice Test 44

Hi PMP aspirants, welcome to AKVTutorials. Looking for a comprehensive set of PMP Project Management Professional practice questions that address the evolving landscape of project management technology? Embrace technological advancements in project management with our practice questions, staying ahead in the evolving landscape of project management technology. In this article, you will get Sample PMP Exam Questions Practice Test 44. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A project to build a new terminal at an airport is ongoing. Currently, the team is performing the plan cost management process. In doing so, which of the following activities might they complete?

Option A : Calculating contingency allowances that will be used to account for uncertainty. 

Option B : Reviewing strategic funding options, such as the possibility of using debt to fund the project.

Option C : Documenting risks that were considered when cost projections were prepared.

Option D : Establishing the amount of management reserve, which will be used to pay for unexpected work

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Reviewing strategic funding options, such as the possibility of using debt to fund the project.

PMP Mock Test Question No 2

Francesco is collecting requirements on a project that involves building a courthouse for a local government. In order to do so, he wants to use a brainstorming method that involves voting on several requirements before they are further prioritized. Which tool or technique would accomplish this task?

Option A : Nominal Group Technique 

Option B : Design of Experiments 

Option C : Brainstorming 

Option D : Focus Groups

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Nominal Group Technique 

PMP Practice Exam Question No 3

A project manager is preparing a scope management plan for a project that includes upgrading three waste-water treatment plants. Which of the following would not be included in that document?

Option A : The steps for decomposing the scope into work packages 

Option B : An explanation of how formal acceptance will be obtained on project deliverables 

Option C : A listing of control accounts and planning packages

Option D : The process for creating the project scope statement

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A listing of control accounts and planning packages

PMP Mock Exam Question No 4

A project manager is leading an effort to design a new 3D printer that accepts a broad range of filament types. During the project, she uses earned value analysis and determines that the CPI is 0.85 and the SPI is 1.25. What does this indicate?

Option A : The project is under budget and ahead of schedule. 

Option B : The project is over budget and behind schedule. 

Option C : The project is under budget and behind schedule. 

Option D : The project is over budget and ahead of schedule.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The project is over budget and ahead of schedule.

Project Management Professional Question No 5

A project manager is working with a team to revitalize a city park. At this point, she needs to understand what currency will be used to pay vendors working on the project. Which document should be reviewed to find this information?

Option A : Procurement Management Plan 

Option B : Cost Management Plan 

Option C : Cost Baseline 

Option D : Procurement Documents

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Procurement Management Plan 

PMP Certification Prep Question No 6

A department store is working on a project to close several locations. During the project, the team spends time decomposing project work into smaller components. What is an output from that process?

Option A : Project Scope Statement 

Option B : Requirements Traceability Matrix 

Option C : Scope Baseline 

Option D : Lessons Learned Register

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Scope Baseline 

PMP Exam Question No 7

On your project, 12 stakeholders have been identified. Based on this information, how many possible communication channels exist?

Option A : 66

Option B : 132

Option C : 72

Option D : 6

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

66

PMP Exam Sample Question No 8

You are managing a project to develop the next version of a popular financial management tool for small businesses. At this point on your project, you are in the process of collecting requirements from stakeholders. One of the tools that will be used are surveys that will be sent to users. Which of the following are inputs of that process? 

Option A : Assumption Log, Requirements Documentation, Project Charter 

Option B : Project Scope Statement, Requirements Documentation, Quality Reports 

Option C : Lessons Learned Register, Requirements Traceability Matrix, Risk Register 

Option D : Project Charter, Lessons Learned Register, Agreements

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project Charter, Lessons Learned Register, Agreements

PMP Exam Practice Question No 9

On a project to landscape the grounds of a large university, the team spends time approximating the number of work periods needed to complete project activities. In this case, what process is being performed?

Option A : Develop Schedule 

Option B : Estimate Activity Durations

Option C : Sequence Activities 

Option D : Create WBS

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Estimate Activity Durations

PMP Certification Exam Question No 10

A project manager is creating a stakeholder engagement plan for a project that involves redesigning the aluminum packaging for a popular soft drink. Which of the following would not be included in that document?

Option A : A formal or informal set of plans for engaging specific stakeholders 

Option B : The classification of known stakeholders 

Option C : Strategies for working productively with those who are impacted by the project 

Option D : A list of tactics for dealing with demanding stakeholders

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

The classification of known stakeholders 

PMP Project Management Professional Practice Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply