PMP Exam Questions Practice Mock Test 33 Answers Keys

Hi PMP aspirants, welcome to AKVTutorials. Are you actively preparing for the PMP exam and want practice questions that align with the agile mindset and principles? Embrace the agile mindset with our PMP Project Management Professional practice questions, aligning your preparation with modern project management principles. In this article, you will get PMP Exam Questions Practice Mock Test 33 Answers Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Which concept of locating team members can help them best to enhance their performance as a team?

Option A : Colocation

Option B : Cross-functional dispersion

Option C : Virtual e-teams 

Option D : Global team dispersion

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Colocation

PMP Mock Test Question No 2

In a lawsuit between your organization and a project contractor, the term “Constructive change” is discussed. Which statements on constructive changes are true?

Option A : Constructive changes are contract changes which are construed from actions taken by either party, not from a change document.

Option B : Changes in projects under contract are called constructive changes if they yield benefits for both parties.

Option C : Constructive changes are a frequent cause of disputes and claims of one contract party against the other.

Option D : Field changes should be meticulously documented to avoid an interpretation as constructive change. 

Option E : Constructive change is a term used civil engineers for claims based on billable changes in building projects.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A, C , D

Constructive changes are contract changes which are construed from actions taken by either party, not from a change document., Constructive changes are a frequent cause of disputes and claims of one contract party against the other., Field changes should be meticulously documented to avoid an interpretation as constructive change. 

PMP Practice Exam Question No 3

You are assigned as a project manager for an internal project. During cost planning and budgeting you discovered that there are peak times of costs during the project and other times when costs are fairly low. What could this mean for the project?

Option A : The fiscal budget mechanism which is used by the performing organization may not allow for cost peaks in your project, and you may have to level out expenditures over time.

Option B : You can silently create budget contingencies during low-cost periods and re-use them later during those periods when you have to cover peak levels in project costs.

Option C : You may find another project manager with a project that has a different rhythm of high and low costs. Then, you may be able to move budget during one project’s low cost periods to the other project.

Option D : You are a project manager and work with a lifecycle budget for your project. Fiscal budgets are a matter of the functional organization, and you generally do not have to care about them.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

The fiscal budget mechanism which is used by the performing organization may not allow for cost peaks in your project, and you may have to level out expenditures over time.

PMP Mock Exam Question No 4

You are going to take over a new project as the project manager in an enterprise unknown to you. What should you investigate during the chartering process?

Option A : Enterprise environmental factors 

Option B : Project management plan 

Option C : Project risk register 

Option D : Team performance reports

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Enterprise environmental factors

Project Management Professional Question No 5

An organization is considering various contract types in order to motivate sellers and to ensure preferential treatment. What should they consider before deciding to use an award fee contract?

Option A : Payment of an award fee would be linked to the achievement of objective performance criteria.

Option B : Any unresolved dispute over the payment of an award fee would be subject to remedy in court.

Option C : Payment of an award fee would be agreed upon by both the customer and the contractor.

Option D : Payment of an award fee is decided upon by the customer based on the degree of satisfaction.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Payment of an award fee is decided upon by the customer based on the degree of satisfaction.

PMP Certification Prep Question No 6

What is least important when it comes to archiving project records? 76

Option A : A well-designed records management system

Option B : Integration of the archive with business software 

Option C : Updated records reflecting final results 

Option D : Easy availability of information for future use

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Integration of the archive with business software 

PMP Exam Question No 7

_______ are not necessarily used to establish the cost baseline of a project.77

Option A : Schedule activity or work package cost estimates.

Option B : The work breakdown structure and the WBS dictionary

Option C : The project schedule and the resource management plan

Option D : The risk breakdown structure and the risk report

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The work breakdown structure and the WBS dictionary

PMP Exam Sample Question No 8

You took over a customer project for your company. From the inputs available, including contract, statement of work and project charter, you have developed a project management plan. You already presented that plan in a meeting with key stakeholders including your project sponsor and some representatives from the customer organization. During the meeting you sensed a high level of dissatisfaction by the customer executives, who signaled that the project might not produce the results that their company had expected. In your understanding, all necessary actions have been planned to meet the customer’s requirements. What should you do next?

Option A : Request a written statement from the customer detailing the requirements which they believe are not addressed by your plan. Use this statement to update the project plan.

Option B : Arrange meetings with the customer to identify their needs, wants and expectations for the project. Then create a narrative Scope statement from this information to document the agreed upon project scope.

Option C : Request a formal meeting on top executive level to get the misunderstandings sorted out, then arrange a change request, re-plan your project where necessary and go ahead with the project work.

Option D : Do not over-react. Performed according to your plan, the project will produce a convincing product for the customer. As soon as the executives will see it, they will probably change their opinion and accept it.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Arrange meetings with the customer to identify their needs, wants and expectations for the project. Then create a narrative Scope statement from this information to document the agreed upon project scope.

PMP Exam Practice Question No 9

What is not true for project deliverables?

Option A : Project deliverables should be identified, described and agreed upon as early in the project as possible. 

Option B : Project deliverables may be products, capabilities for services or other kinds of results. 

Option C : Once project deliverables have been identified, their description should not be changed any more. 

Option D : The acceptance process for deliverables and how rejection will be addressed should be described in the contract

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Once project deliverables have been identified, their description should not be changed any more. 

PMP Certification Exam Question No 10

Your project, performed for a customer, is coming to an end. The customer has been contractually granted a three years warranty period for the product of the project. What should you do first?

Option A : Hand all relevant documentation over to the organizational unit responsible for handling the warranty.

Option B : There is no additional work to be done. The contract should describe all processes in sufficient detail.

Option C : Changes on the product can affect warranty clauses. Ensure that these clauses are aligned with the final specifications.

Option D : According to many legislations, you cannot formally close a project before the end of the warranty period.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Changes on the product can affect warranty clauses. Ensure that these clauses are aligned with the final specifications

PMP Exam Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply