PMP Exam Prep Test 32 Questions Bank Answers Keys Explanations

Hi PMP aspirants, welcome to AKVTutorials. In need of PMP Project Management Professional practice questions that focus on procurement management and contract types? Master procurement management and contract types with our PMP practice questions, essential components of Project Management Professional success. In this article, you will get PMP Exam Prep Test 32 Questions Bank Answers Keys Explanations. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Following the cultural approach of the corporation for which you are starting to manage a project, you are guiding your project team through the first life-cycle phase of conceptualization. Your next step is to call for a team meeting to let ideas emerge in an unrestricted creative process. What exactly should that look like?

Option A : You write down the ideas of team members and structure them into categories of strengths, weaknesses, opportunities and threats during the session.

Option B : You creatively gather thoughts and ideas without any discussion or frowning. These ideas are only filtered and structured after the end of the brainstorming session

Option C : Your team members wear hats with different colors, each of which stands for a way of thinking. Each member discusses topics from the viewpoint of their thinking. 

Option D : You try to eradicate deviating ideas and concepts of team members during the meeting, so that the entire project team follows your principles

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

You creatively gather thoughts and ideas without any discussion or frowning. These ideas are only filtered and structured after the end of the brainstorming session

PMP Mock Test Question No 2

In configuration management, which of the following is necessary to maintain the integrity of baselines?

Option A : Analyzing variances by comparing baseline information with actual project data.

Option B : Releasing only approved changes for incorporation into products or services. 

Option C : Ensuring that team members adhere to a code of ethical conduct and behavior. 

Option D : Ensuring transparency across all project management processes and activities.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Quality control measurements and work performance information

PMP Practice Exam Question No 3

A representative of your customer approached you this morning referring to a part of your team that works on customer’s premises. She complained that your team members do not fully blend with her staff and that there are conflicts originating in different corporate cultures of your organization and hers. She demanded that you motivate them to display more stewardship What is she referring to? (Choose 3)

Option A : Care 

Option B : Respect

Option C : Diligence 

Option D : Tayloring

Option E : Formal leadership

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A , B , C

Care, Respect , Diligience

PMP Mock Exam Question No 4

Which is not a point used for three-point estimation?

Option A : Optimistic estimate 

Option B : Most likely estimate 

Option C : Budget estimate 

Option D : Pessimistic estimate

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Budget estimate 

Project Management Professional Question No 5

Which of the following are not common barriers to project team building?

Option A : Differing outlooks, priorities, and interests 

Option B : Role conflicts

Option C : Excessive team member commitment 

Option D : Unclear project objectives/outcomes

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Excessive team member commitment 

PMP Certification Prep Question No 6

During project planning, you are presented with the following diagram that depicts a cumulative likelihood distribution for the duration of a project. What kind of conclusion can you draw from the information depicted in it?

 

Option A : The likeliness that the project will finish exactly at the date marked with “Deadline” is 80%

Option B : The likeliness that the project team will exceed the date marked with “Deadline” is at 80%.

Option C : If the project team will meet the deadline, project costs will be 80% of the budgeted costs. 

Option D : The likeliness that the project team will meet the deadline or will finish earlier is at 80%

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

 The likeliness that the project team will meet the deadline or will finish earlier is at 80%.

PMP Exam Question No 7

While executing a project, you sense a slightly negative attitude in your team. Which type of document do you now need, among others, to better understand and then be able to improve the situation?

Option A : Project charter

Option B : Team performance assessments 

Option C : Cost baseline 

Option D : Statement of work

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Team performance assessments 

PMP Exam Sample Question No 8

The sales representative of your company recently contacted you. You made some estimates on direct costs for an offer on a firm fixed-price contract. According to company policies, indirect costs (overheads) are to be calculated as a percentage of the direct costs, the sum of both cost types caused him to calculate a far too high price. How should you not react?

Option A : You reduce your direct cost estimates by reducing the amount of work and the rates allocated to them. This allows a reduction of the overhead costs and a lower price.

Option B : Calculating overheads as a percentage of direct costs is just a model to simplify calculations. A more specific analysis of these costs may lead to a more realistic project price. 

Option C : Cost estimates are quantitative assessments of the probable costs required to complete project work. These are made by the project team. It is the sales person’s job to make the price.

Option D : You make the sales person aware that a reduction of direct costs may reduce the numbers for overhead cost allocation, but will not influence the actual overheads.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

You reduce your direct cost estimates by reducing the amount of work and the rates allocated to them. This allows a reduction of the overhead costs and a lower price.

PMP Exam Practice Question No 9

A project charter is a document that…

Option A : …describes both the project scope and the product scope at detail level.

Option B : …authorizes the project and the use of organizational resources to meet project requirements. 

Option C : …breaks down the project scope over several steps to describe the project on work package level.

Option D : …describes all activities which are necessary to create the project deliverables.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

…authorizes the project and the use of organizational resources to meet project requirements. 

PMP Certification Exam Question No 10

You identified a technical risk in your project and assigned a contingency for that. Planning contingency reserves is part of which risk response strategy?

Option A : Active risk mitigation 

Option B : Passive risk avoidance 

Option C : Passive risk acceptance 

Option D : Active risk acceptance

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Active risk acceptance

PMP Mock Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply